Redwood Road Update: 7/31/09
Friday, July 31, 2009
Early next week, the new signal at 14400 S. will be ready for activation. During this switch the intersection will be controlled by flaggers. Please watch for and follow flaggers’ directions as the new signal is activated and the old removed.
General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68. Asphalt crews continue working at night in several areas of the project next week. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas. Weather and schedule permitting, daytime paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place.
Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed and paving occurs across accesses. Notice will be given of longer-term impacts. Approved roadside mailboxes are being placed along the project in coming weeks. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense.
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
Early next week, the upgraded signal at 14400 S. will be activated. The intersection will be directed by flaggers while the switch is made. Utility and earthwork will continue this week at Rose Creek. Work on this structure is scheduled to be complete late next week. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Both night and day crews are scheduled to pave in this segment several days next week. Working both shifts will expedite paving operations and limit impacts to peak traffic. Paving operations are weather dependent.Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route.
Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email:
widen73@hotmail.comSegment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving and FDR operations are scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. This project also has separate flagging operations, and motorists should expect delays as a result. If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email:
access@utah.govGeneral Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to
sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion.
Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
Saratoga Springs 2009 Voting Precincts
Wednesday, July 29, 2009
SR01Sunrise Meadows, Sunset Haven, Sierra Estates, The Benches, Saratoga HIlls, Lakeview Terrace.
SR02Loch Lomond, Saratoga Springs Development
SR03Jacobs Ranch, Lakeside, Stillwater, Summerhill, Fox Hollow, The village of Hawks Landing, The Villages of Hawks Ranch, Lake Mountain Estates, Pelican Bay, Harbor Bay.
SR04Aspen Hills, Dalmore Meadows, Harvest Hills, Summer Village, the Cove at Jordan river, The Springs at Harvest Hills, Sergeant Court, Riverbend
SR05Harvest Hill, Saratoga Chase
SR01, SR02 and SR03 voting will be held at the Saratoga Shores Elementary School, 1415 South Parkside Drive.SR04 and SR05 voting will be held at the Harvest Hill Elemenetary School, 2105 North Providence Drive.
Redwood Road Update: 7/23/09
Thursday, July 23, 2009
Crews are paving today on the west side of the intersection at 14400 S. and plan to have that leg of the intersection reopened to traffic for the holiday. In coming weeks, a second layer of asphalt will need to be placed in this area, during which time access will again be limited. When more details about that closure become available they will be included in this weekly update.
At the completion of today’s construction activities, work will be suspended over the long weekend as crews observe the Pioneer Day holiday. Work will pick up again on Sunday night with nighttime paving operations. Please continue to observe posted safety measures and follow traffic control devices to ensure a safe, enjoyable holiday weekend for everyone.
General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68.
Asphalt crews continue working at night in several areas of the project next week. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas. Weather and schedule permitting, daytime paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place.
Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
The west leg of the 14400 S. intersection will be reopened to traffic for the holiday weekend. Thank you for your patience during this work. (See details above) Utility and earthwork will continue this week at Rose Creek. Work on this structure is scheduled to be complete late next week. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Both night and day crews are scheduled to pave in this segment several days next week. Working both shifts will expedite paving operations and limit impacts to peak traffic. Paving operations are weather dependent.Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Drilling/trenching activities will continue this week on the west side of the road north of Harvest Hills for gas line installation. Residents in this area may experience increased noise and vibration levels as crews trench through rocky areas. Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email:
widen73@hotmail.comSegment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving and FDR operations are scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. This project also has separate flagging operations, and motorists should expect delays as a result. If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email:
access@utah.govGeneral Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to
sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion. Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
Mosquito Abatement
Monday, July 20, 2009
The City has
received some calls regarding Mosquito Abatement. Mosquito abatement is currently done through Utah County. Each year they spray the edge of the lake by air several times throughout the Summer. Anything else is done on a request basis. If you would like to make a request for spraying please contact Utah County
Mosquito Abatement at (801) 851-7637.
UVU Communnity Education Classes-Instructors Needed
Wednesday, July 15, 2009
Community Education Announcement
Community Education classes, through Utah Valley University (UVU), is coming to our community this fall!
These classes are designed to be fun (short-term, no test or term papers) and to enrich the lives of the members of our community. Most of the community education classes will be held in the evening at our new Westlake High School in Saratoga Springs (Redwood Road and Pony Expressway). In order to offer as many classes as possible, potential teachers are asked to contact Bud Poduska (Community Education Coordinator for the Saratoga Springs/Eagle Mountain/Lehi area):
Instructors do not have to be certified teachers, merely competent in their areas of expertise and enthusiastic about teaching others. In most cases, the classes will be held at Westlake High School once a week (Tues-Wed.-Thus.), evenings (Between the hours of 6 and 8:30), for 1 or 2 hours, over as many sessions as needed (Usually 3 to 6 to 8). The first fall classes will not begin until September 14th; the second set of classes will begin October 20th.
The wages will not be enough to support a family but should be sufficient to pay many of your utility bills. The following is a list of potential classes, however, if you have an area of expertise that you think others may be interested in learning, feel free to offer a proposal.
Arts & Crafts
Beginning Drawing Charcoal Drawing sketching
Advance Drawing
Watercolor: beginning/intermediate
Oil painting: beginning/intermediate
Picture framing
Wheel throwing ceramics
Sculpting
Digital Scrapbooking
Cooking & Home Improvements
Sports & Fitness
Business & Finance
Computers
Health & Wellness
Language
Spanish
Chinese
Italian
German
Music
Personal & Family Growth
Creative Writing
Writing your 1st book
Publishing your 1st book
Photography
Hobbies & Special Interest
Redwood Road Update: 7/15/09
Wednesday, July 15, 2009
Beginning today crews will close the west side of the intersection at 14400 S. in order to expedite intersection reconstruction. (See details below)
Asphalt crews will continue working at night in several areas of the project this week to accelerate paving operations. (See details below)
General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68.
Asphalt crews continue working at night in several areas of the project this week. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas. Weather and schedule permitting, daytime paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place. Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
In order to complete excavation and paving work, the west half of the intersection at 14400 S. will close beginning today for approximately one week. Motorists should follow posted detours. Watch for intermittent flagging operations as needed in the intersection. Thank you for your patience during this work. Crews are beginning preparatory work for the new signal poles at 14400 S. This work will take place outside the roadway and should have minimal impact to traffic. Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent.Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Work on the sound wall at Dalmore Meadows resumes this week. Residents may experience some additional noise and vibration while this work is completed. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. The signal at Harvest Hills is now active. Please drive carefully in this area. Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email:
widen73@hotmail.comSegment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. This project also has separate flagging operations, and motorists should expect delays as a result. If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email:
access@utah.govGeneral Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to
sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion. Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
Redwood Road Update: 7/9/09
Thursday, July 09, 2009
This Saturday and Sunday, July 11 & 12, the east side of the intersection at 14400 S. will be closed. This will allow the crews to reconstruct the east half of the intersection more quickly. (See details below)
In order to expedite paving activities, an asphalt crew is scheduled to begin working at night in several areas of the project this Sunday, July 12. (See details below)
General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68.
An asphalt crew is scheduled to begin working at night in several areas of the project this Sunday night. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas.Weather permitting, paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place. Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
This Saturday and Sunday, July 11 & 12, the east side of the intersection at 14400 S. will be excavated and paved. In order to complete this work, the east half of the intersection will be closed, including access to and from 14400 S. on this side. Also, 1700 W. will be reduced to one direction at a time in the area. Residents should plan to take alternate routes to access SR-68. Both 14400 S. and 1700 W. will be controlled by flaggers during this time. Thank you for your patience during this work. Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions. Paving operations are also scheduled to be completed on the north end of the project near Bangerter this week. Paving work is weather dependant.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Crews will be installing pipe near the new signal at Camp Williams this week. In order to safely install these materials it may be necessary to temporarily disable the signal. Please watch for outages at this intersection early next week, during which the intersection will be controlled by flaggers. Paving is scheduled in this segment several days next week. Paving operations are weather dependent.
Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. The signal at Harvest Hills is now active. Please drive carefully in this area.
Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is currently underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email:
widen73@hotmail.comSegment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. This project also has separate flagging operations, and motorists should expect delays as a result. If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email:
access@utah.govGeneral Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to
sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion. Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
Redwood Road Update: 7/2/09
Thursday, July 02, 2009
In observance of the Fourth of July holiday, crews will be minimal on Friday, July 3, and no work will occur on Saturday, July 4. Please note that traffic control measures will remain in place during this time for safety reasons so motorists travelling through the area should still plan for some delays over the holiday weekend.
In order to expedite paving activities, an asphalt crew is scheduled to begin working at night in several areas of the project at the end of next week. (See details below)
General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68.An asphalt crew is scheduled to begin working at night in several areas of the project at the end of next week. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas. Weather permitting, paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place.
Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions. Paving work is scheduled in this segment several days next week. Paving operations are weather dependent.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Excavation and grading crews will continue widening the roadway in the area of Camp Williams this week.
Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. Activation of the new signal at Harvest Hills remains pending a power connection.
Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email:
widen73@hotmail.comSegment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area traffic has increased. This project also has separate flagging operations, and motorists should expect delays as a result.
If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email:
access@utah.govGeneral Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to
sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion.
Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.
UVU Coming to Saratoga Springs Fall 2009
Wednesday, July 01, 2009
Take Classes Closer to Where You Live
Utah Valley University will be offering 8 evening classes at the new
Westlake High School in
Saratoga Springs starting Fall Semester 2009.
Classes will start at 5:40 pm or 6:00 pm on Tuesday and Thursday evenings . Courses in Business, Chemistry, English, Math, and Science will be offered and most will be taught by faculty from
Westlake High School.
These classes are full academic credit courses at
UVU that apply to general education requirements.
For more information, contact Ruth
Gowans at (801) 863-6216 or at
gowansru@uvu.edu or visit the web at
www.uvu.edu/extend.