Redwood Road Project Update: 2/25/09
SPECIAL ALERT: Beginning today at 9 a.m. crews will install a sewer line in the area of Harvest Hills. During this work traffic will be limited to one direction at a time. This work is scheduled to conclude at 3 p.m. today and will resume again tomorrow (Thursday) from 9 a.m. – 3 p.m. Thank you for your patience during this work.
As a reminder, we are conducting a mid-construction survey and we would like to hear from you! If you haven’t completed a survey with us yet, please click on the link below to participate in our brief online survey, which will be available through February 27. If you would prefer to receive a hard-copy survey by mail, please contact us at 801-455-3116.
SR-68 Mid-Construction Survey
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper. The east leg of the intersection at 14400 South has been widened and traffic shifted to the north in order to allow work to begin on the canal below. Please note that due to this shift in alignment, the timing of the traffic signal at this intersection has been adjusted to allow safe left turn movements. The project team is working to optimize the timing of the light to minimize congestion, but motorists should plan for some extra travel time in this area. The adjusted timing is scheduled to last through April. Thank you for your patience.
Crews will continue excavation activities on the hill near the northwest corner of 14400 S. and SR-68 and have now begun installation of the decorative retaining wall. Work will be limited to the shoulder of the road. Work on the irrigation canals throughout this segment will continue this week. Work on a number of utilities in this segment is also continuing.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Crews will continue excavating near Camp Williams this week. Canal work is ongoing in all areas of Segment 3 this week.
Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Beginning today at 9 am crews will install a sewer line in the area of Harvest Hills. During this work traffic will be limited to one direction at a time. This will work is scheduled to conclude at 3 pm today and will occur again tomorrow (Thursday) from 9 a.m. – 3 p.m. Crews will continue installing the storm drain system in this segment this week.
Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs. Pipe crossings for the storm drain system will continue this week as weather allows. During this operation, traffic will be limited to one direction at a time under the direction of flaggers between the hours of 9 a.m. and 3 p.m. Thank you for your patience in this area.
Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area, increased traffic is expected.
As a reminder, we are conducting a mid-construction survey and we would like to hear from you! If you haven’t completed a survey with us yet, please click on the link below to participate in our brief online survey, which will be available through February 27. If you would prefer to receive a hard-copy survey by mail, please contact us at 801-455-3116.
SR-68 Mid-Construction Survey
Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper. The east leg of the intersection at 14400 South has been widened and traffic shifted to the north in order to allow work to begin on the canal below. Please note that due to this shift in alignment, the timing of the traffic signal at this intersection has been adjusted to allow safe left turn movements. The project team is working to optimize the timing of the light to minimize congestion, but motorists should plan for some extra travel time in this area. The adjusted timing is scheduled to last through April. Thank you for your patience.
Crews will continue excavation activities on the hill near the northwest corner of 14400 S. and SR-68 and have now begun installation of the decorative retaining wall. Work will be limited to the shoulder of the road. Work on the irrigation canals throughout this segment will continue this week. Work on a number of utilities in this segment is also continuing.
Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Crews will continue excavating near Camp Williams this week. Canal work is ongoing in all areas of Segment 3 this week.
Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Beginning today at 9 am crews will install a sewer line in the area of Harvest Hills. During this work traffic will be limited to one direction at a time. This will work is scheduled to conclude at 3 pm today and will occur again tomorrow (Thursday) from 9 a.m. – 3 p.m. Crews will continue installing the storm drain system in this segment this week.
Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs. Pipe crossings for the storm drain system will continue this week as weather allows. During this operation, traffic will be limited to one direction at a time under the direction of flaggers between the hours of 9 a.m. and 3 p.m. Thank you for your patience in this area.
Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area, increased traffic is expected.
If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email: access@utah.gov
General Project Information:
Please remember that passing is strictly prohibited throughout the work zone.
Now that the weather is getting warmer, many more crews will continue to be added and hours of work will expand. Crews are now working Monday – Saturday, nine hours per day.
Recreational activities such as biking and jogging are strongly discouraged in the construction area due to the narrow lanes.
Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
More Information
For additional project information, visit www.udot.utah.gov/sr-68south. For specific questions or concerns, contact the Public Information Team at sr68info@langdongroupinc.com or 801-455-3116.
Hotline: 877-222-3757
Email: access@utah.gov
General Project Information:
Please remember that passing is strictly prohibited throughout the work zone.
Now that the weather is getting warmer, many more crews will continue to be added and hours of work will expand. Crews are now working Monday – Saturday, nine hours per day.
Recreational activities such as biking and jogging are strongly discouraged in the construction area due to the narrow lanes.
Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
More Information
For additional project information, visit www.udot.utah.gov/sr-68south. For specific questions or concerns, contact the Public Information Team at sr68info@langdongroupinc.com or 801-455-3116.