A date for the Harvest Hills Blvd. reconstruction project is
scheduled to start work on the 16
th of June. Mitchell Excavating will be rebuilding the road from the round-a-bout on Providence Drive
thru the round-a-bout on Harvest Moon Dr. the project is expected to last approximately 45 days. Two way traffic in the west bound lane will be maintained during the duration of the project. For questions or concerns regarding this project please contact the Engineering department at 766-6504.
UDOT Notice-SR 73 near 3130 West
Thursday, May 08, 2008
May 12-Construction will begin on a box culvert under SR 73 as part of a Jordan River Trail Enhancement. Traffic will be restricted to one lane in each direction with lower speed limits through the construction zone.
Public comments or questions can be directed to the Public Information Coordinator, Scott Thompson at
UDOT Region 3 Headquarter, (801) 227-8006 or
scottthompson@utah.gov