Redwood Road Update: 7/2/09

Thursday, July 02, 2009

In observance of the Fourth of July holiday, crews will be minimal on Friday, July 3, and no work will occur on Saturday, July 4. Please note that traffic control measures will remain in place during this time for safety reasons so motorists travelling through the area should still plan for some delays over the holiday weekend.

In order to expedite paving activities, an asphalt crew is scheduled to begin working at night in several areas of the project at the end of next week. (See details below)

General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68.An asphalt crew is scheduled to begin working at night in several areas of the project at the end of next week. The lower traffic volumes at night will allow larger stretches of asphalt to be placed at one time. Night paving is scheduled primarily in non-residential areas. Weather permitting, paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place.
Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.

Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions. Paving work is scheduled in this segment several days next week. Paving operations are weather dependent.

Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Excavation and grading crews will continue widening the roadway in the area of Camp Williams this week.

Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. Activation of the new signal at Harvest Hills remains pending a power connection.
Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email: widen73@hotmail.com

Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area traffic has increased. This project also has separate flagging operations, and motorists should expect delays as a result.
If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email: access@utah.gov

General Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion.
Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.


UVU Coming to Saratoga Springs Fall 2009

Wednesday, July 01, 2009

Take Classes Closer to Where You Live
Utah Valley University will be offering 8 evening classes at the new Westlake High School in Saratoga Springs starting Fall Semester 2009.
Classes will start at 5:40 pm or 6:00 pm on Tuesday and Thursday evenings . Courses in Business, Chemistry, English, Math, and Science will be offered and most will be taught by faculty from Westlake High School.
These classes are full academic credit courses at UVU that apply to general education requirements.
For more information, contact Ruth Gowans at (801) 863-6216 or at gowansru@uvu.edu or visit the web at www.uvu.edu/extend.


2009 Election Information

Monday, June 29, 2009

This year there are two (2) Council positions and one (1) Mayoral position to be voted on. They are all four-year terms (January 2010-January 2014).

FILING PERIOD: The filing period begins on July 1, 2009 and ends promptly at 5:00 p.m. on July 15, 2009.
The candidate filing period is from July 1 through July 15, 2009, at the City of Saratoga Springs Recorder's Office, 1307 North Commerce Drive, Suite 200, Saratoga Springs. Office hours are Monday through Friday, 8:00 a.m to 5:00 p.m. (The office will be closed on Friday, July 3, 2009 in observance of Independence Day).

**PRIMARY ELECTION** September 15, 2009 (if needed)
Early voting will be from Tuesday, September 1st through Friday, September 11, 2009

**GENERAL ELECTION** November 3, 2009
Early voting will be from Tuesday, October 20th through Friday, October 30, 2009.

Polls shall be open from 7 a.m. to 8 p.m.

If you have questions, please call the City Recorder at (801) 766-9793 ext. 103)

What are the requirements to run for office?

  • Must be 18 years old
  • A US citizen
  • A registered voter
  • A resident of Saratoga Springs (or a recent annexation area) for twelve consecutive months prior to the elections.

POLL WORKERS: The City of Saratoga Springs has a need for election poll workers to assist voters during the upcoming elections. If you're interested, you may call Lori Yates, City Recorder at 801-766-9793 ext 103 or email at lyates@saratoga-springs.net.



Redwood Road Update: 6/25/09

Thursday, June 25, 2009

This week traffic on the north end of the project, near Bangerter Highway will be shifted to the west side of the road. Due to this shift, a second left hand turn pocket will again be available for the eastbound Bangerter to northbound Redwood turn movement.

General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68. Weather permitting, paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place. Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.

Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
Traffic on the north end of the project near Bangerter will shift this week. (See details above)
Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions. Paving work is scheduled in this segment several days next week. Paving operations are weather dependent.

Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Excavation and grading crews will continue widening the roadway in the area of Camp Williams this week. Traffic shirts will occur as part of this work, please watch for these changes.

Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. Motorists should expect traffic shifts along SR-73 and SR-68 late this week and early next week as work progresses to new areas in the intersection. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses.
Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. Activation of the new signal at Harvest Hills is pending a power connection. Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email: widen73@hotmail.com

Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Traffic will remain shifted to the east this week in the vicinity of 400 N. until installation of the water line casing is completed. Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area traffic has increased. This project also has separate flagging operations, and motorists should expect delays as a result. If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email: access@utah.gov

General Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion.
Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.

Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.

More Information
For additional project information, visit www.udot.utah.gov/sr-68south. For specific questions or concerns, contact the Public Information Team at sr68info@langdongroupinc.com or 801-455-3116.


Redwood Road Update: 6/18/09

Thursday, June 18, 2009

This Sunday, June 21, at 14400 S. traffic in all directions will be limited to one lane to accommodate paving operations. All turn movements will be allowed, but motorists should expect delays.

General Impacts – Corridor-wide impacts from activities occurring along the entire stretch of SR-68. Weather permitting, paving operations will be underway at various locations throughout the project this week. Please watch for shifting traffic and brief access interruptions as this work takes place. Residents and businesses should expect brief, intermittent access interruptions as curb, gutter and sidewalk are installed across accesses. Notice will be given of longer-term impacts.

Segment 4 - Beginning just south of the intersection at Bangerter Highway and ending at the south end of Bluffdale proper.
This Sunday, June 21, traffic will be limited to one lane in all directions. See above for details.
Utility and earthwork will continue this week at Rose Creek. Traffic shifts will continue while the structure beneath the road is completed. Concrete crews are installing curb, gutter, sidewalk and driveway approaches this week. Residents will experience brief access interruptions. Paving work is scheduled in this segment several days next week. Paving operations are weather dependent.

Segment 3 - Beginning south of Bluffdale and ending just south of Camp Williams.
Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Excavation and grading crews will continue widening the roadway in the area of Camp Williams this week.

Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Excavation, utility work and paving are ongoing in the intersection of SR-73/SR-68. Motorists should expect traffic shifts along SR-73 and SR-68 late this week and early next week as work progresses to new areas in the intersection. One through lane and one left turn lane will be maintained in all directions during construction at SR-73/SR-68. We understand that the delays at this intersection are inconvenient; we appreciate your patience as work progresses. Note that the sidewalk on the southeast corner of the Crossroads intersection remains closed to ensure pedestrian safety. Please plan an alternate walking route. The new signal at Harvest Hills is scheduled for activation late next week. Please use caution when driving in the area. Be aware that another project to improve SR-73 from Redwood Road to 800 West in Saratoga Springs is now underway. For more information about this project, please contact their Public Information Team:
Phone: 1-888-427-8585
Email: widen73@hotmail.com

Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Traffic will be shifted to the east this week in the vicinity of 400 N. to accommodate installation of a water line casing. Paving is scheduled in this segment several days next week. Paving operations are weather dependent. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs. With the addition of another project in the area traffic has increased. This project also has separate flagging operations, and motorists should expect delays as a result.
If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email: access@utah.gov

General Project Information
As a reminder, the SR-68 project has initiated a text messaging update service for interested stakeholders. If you would like to receive real-time text messages regarding high priority changing conditions (emergency road closures and other time sensitive updates), please send a request to sr68info@landgdongroupinc.com. Please include your wireless phone number and mobile provider name. Standard text messaging rates apply. This service will extend through project completion.
Please remember that recreational activities such as biking and jogging are strongly discouraged in the construction area for your safety and the safety of the crews.
The project is still progressing on schedule for completion by fall 2009.