Required Inspections
| Temporary Power | After temporary power pedestal has been placed and an 8 foot rod has been driven into the ground. |
| Footing | After footings have been dug or formed and re-bar has been placed. |
| Foundation | After forms have been set and re-bar has been placed. |
| Ground Plumbing | After all piping has been installed, system is being tested, and before backfilling |
| Sewer Lateral | After sewer lateral has been installed, pipe bedded and test set on system. |
| Rough Plumbing | After all drains, vents and water piping has been installed and is being tested. |
| Rough Mechanical | After vents, chimneys, heat ducts and combustion air ducts that will not be exposed for final inspection have been installed. |
| Rough Electrical | After wire has been run and boxes, including breaker panel, have been made up. |
| Framing | After framing is complete, including the installation of doors and windows. Before starting any brick, stone, stucco, siding or insulation. |
| Insulation | After Insulation, except blown in attic, has been installed and foam has been applied around windows, doors, floor and ceiling penetrations etc. |
| Sheetrock | After sheetrock has been nailed/screwed, before taping. |
| Stucco | After all weather barriers, flashing and wire has been installed and before brown coat has been applied. |
| Final | After building is complete and ready for occupancy. This includes grading, concrete, floor coverings, painting, caulking, house numbers in correct location and landscaping when required. This also includes repair or replacement of damaged off-site improvements that are adjacent to your lot. |
All inspections shall be requested at least one working day in advance before 4:00 PM
To schedule inspections please contact angela in the building department at (801) 766-6507